Question 1.
What are number of communication channels possible in a project with Team size of 8

Answer 1 .
If n is the number of people in project, then there are n(n-1)/2 communication channels in the project
Hence Answer is 8(8-1)/2 = 28

Question 2.
What is Parametric estimating ?

Answer 2.
Parametric estimating is the process of using historical data to compare against your project to determine a correlation and thereby a cost estimate for your current project

Question 3.
What is output of Plan Quality process ?

Answer 3.
Outputs of Plan Quality process includes :

  1. Quality Management Plan
  2. Quality Metrics
  3. Quality Checklists
  4. Process Improvement Plan
  5. Project Document Updates